Work continues on campus

Work+continues+on+campus
Robert Jerrod Brown

The current construction behind the Administration Building is part of the new Campus Security Project.

A brick screen will be built behind the building to protect the air systems and equipment running the Computing Center.

The project is funded by the state and costs about $3 million, said Jason Roubique, Director of Facilities Management. The Computing Center is on the first floor and hosts the majority of the servers for computer and security systems on campus.

A new generator will also be installed to allow systems to continue working in the event of a power outage.

The Campus Security Project includes improvements to sur and specifically an emergency siren system.

The project should be finished by June 2011.